July 2021

Approval of Italy's National Recovery and Resilience Plan (NRRP)

Approvazione del Piano Nazionale di Ripresa e Resilienza (Pnrr) dell'Italia

13 July 2021 - Italy's Plan is approved by means of a Council of the European Union Implementing Decision, which transposed the Commission's proposal. In the Decision are defined, in relation to each investment and reform, precise objectives and targets, cadenced in time, to the achievement of which is linked the allocation of resources on a six-month basis.

Past Event
August 2021

Allocation of resources to the Civil Protection Department

Ripartizione risorse assegnate al Dipartimento della Protezione Civile

6 August 2021 - Assigned to the Civil Protection Department, by Decree of the Ministry of Economy and Finance, within the framework of Mission 2, Component 4, sub-investment 2.1 b "Measures for flood risk management and hydrogeological risk reduction", 1.2 billion euro, divided between 400 million euro for existing projects and 800 million euro for new projects.

Past Event
December 2021

Achievement of EU Milestone M2C4-12

Raggiungimento Milestone Ue M2C4-12

31 December 2021 - Lists of existing projects and macro-interventions for new projects approved.

Milestone M2C4-12 "Entry into force of the revised legal framework for interventions against flood and hydrogeological risks", concerning the recognition and approval of Regional Investment Plans against flood and hydrogeological risks, has been achieved. The documents are published on the institutional websites of the Civil Protection Department and the Regions and Autonomous Provinces or the delegated Commissioners.

Past Event
August 2022

Defining the procedures for the allocation of funds for new projects

Definizione delle modalità di assegnazione dei fondi per i nuovi progetti

23 August 2022 - Definition of the procedures for the allocation and transfer to the Regions and Autonomous Provinces of Trento and Bolzano of the financial resources for the new projects, with Decree of the President of the Council of Ministers issued pursuant to art. 22 of Law Decree no. 152 of 6 November 2021.

Past Event
October 2022

Approval of the detailed lists of new projects

Approvazione degli elenchi di dettaglio dei nuovi progetti

October 2022 / January 2023 - 21 decrees were issued by the Head of the Department, one for each Region and Autonomous Province, approving the detailed lists of new projects.

Past Event
December 2022

Achievement of the national monitoring step

Raggiungimento Monitoring step nazionale

The national objective (monitoring step) of allocating 40% of the planned public contracts was achieved.

Past Event
January 2023

Subscription of agreements

Sottoscrizione degli accordi

January 2023 / ongoing - Agreements are signed, pursuant to art. 15 of Law No. 241/1990, between the Department and the Regions and Autonomous Provinces, to regulate the collaborative development of activities of common interest, through a clear division of responsibilities and obligations related to the management, monitoring, reporting and control of the interventions eligible for funding.

Past Event
March 2023

Transfer of resources in advance

Trasferimento delle risorse a titolo di anticipazione

March 2023 / ongoing - Amounts up to 10% of the total allocated for new projects are transferred to the Regions and Autonomous Provinces in the form of advance payments.

Past Event
November 2023

Publication of calls for tenders for new projects

Pubblicazione dei bandi di gara per i nuovi progetti

30 November 2023 - Publication of calls for tenders or start of the awarding procedure, pursuant to Article 3, Paragraph 2 of the Prime Ministerial Decree of 23 August 2022, as amended by Article 29 of Decree-Law No. 13/2023.

Past Event
March 2024

Stipulation of the contract for new projects

Stipula del contratto di appalto per i nuovi progetti

31 March 2024 - Stipulation of the tender contracts, pursuant to Article 3, paragraph 2 of the Prime Ministerial Decree of 23 August 2022, as amended by Article 29 of Decree-Law No. 13/2023.

Past Event
April 2024

Actual start of works for new projects

Inizio effettivo dei lavori per i nuovi progetti

15 April 2024 - Effective start of works, pursuant to Article 3, paragraph 2, of the Prime Ministerial Decree of 23 August 2022, as amended by Article 29 of Decree-Law No. 13/2023

Past Event
June 2024

Achievement of the national monitoring step

Raggiungimento Monitoring step nazionale

The national objective (monitoring step) of allocating 80% of the planned public contracts was achieved.

Past Event
December 2024

Achievement of national target M2C4 ITA-8

Raggiungimento Target nazionale M2C4 ITA-8

90% of the planned public contracts for types D and E interventions were successful. The result, scheduled for June 2025, was achieved ahead of time.

Future event
June 2026

EU target M2C4-13

Target Ue M2C4-13

The completion of 90% of type D and E interventions for recovering damaged public structures identified by the approval acts of the National Civil Protection Service is planned.

Future event
December 2026

National target M2C4 ITA-10 and M2C4 ITA-11

Target nazionale M2C4 ITA-10 e M2C4 ITA-11

The completion of 98% of type D and E interventions for recovering damaged public facilities identified in the approval acts of the National Civil Protection Service is planned.